Satsop School summer progress
Project updates · August 23, 2025
In summer 2025, construction advanced across the Satsop School campus while the district prepared to hold classes at its temporary Satsop Business Park location.
By the August update, underground utility work was complete. Concrete footings were in place for the new gym and the accessible ramp on the north side of the main building.
Inside the historic schoolhouse, crews removed the old carpet and began restoring the original wood floors. The school bell was being restored off site, with its return to the belfry planned as work continued.
Rock supports the district with program, project, and construction management. This update records the project’s progress in August 2025.