On site, there is a total of 3 overall buildings; the main building, the maintenance shed, and finally, the gymnasium/dining building that is adjacent/abutting to the covered play building.
Proposed Improvements
The following items present the General Work of Scope.
Work Item 1. Insulation [AS FUNDS ALLOW].
-
Reduce energy consumption and improve comfort of indoor spaces.
-
Add new insulation to all heated areas.
-
Add insulation in attic areas, exterior walls, and crawl spaces.
-
Add vapor barriers and ventilation where needed.
-
Add heat trace to pipes susceptible to freezing.
-
Add caulking around windows and at other exterior building enclosure penetrations.
-
Review acoustics of indoor areas and add acoustic insulation or panels if/where needed.
-
Work Item 2. Electrical systems upgrade.
-
Provide reliable, safe, and efficient electrical systems throughout the District facilities.
-
Provide new electrical distribution panels, circuits, conduits and wiring, new convenience power/data outlets, low voltage wiring, lighting, lighting fixtures, audio/video system, security system, data and Wi-Fi, and fire alarm/life safety system upgrades.
-
Work Item 3. Structural upgrades [AS FUNDS ALLOW].
-
Upgrade structural systems for improved long-term structural integrity.
-
Replace the current direct-bury shallow wood foundation with new wood, steel, or concrete pilings or piers, and/or a concrete perimeter foundation and interior columns and bearing walls, columns, beams, and roof members to comply to improve the seismic structural connections throughout the buildings.
-
The design will consider least obtrusive improvements to maintain the historical character, use of facilities as instructional and assembly spaces, and cost long-term safety of the facilities.
-
Work Item 4. Update interior finishes.
-
Update interior flooring and wall coverings to preserve and enhance the indoor aesthetics, acoustics, cleanliness, durability, and ease of maintenance of interior spaces.
-
Provide carpet tile and acoustic wall panels and other wall finishes to improve interior appearances where aging systems are worn and need of replacement.
-
Provide new paint and other finishes throughout the interior spaces, with materials and supplies that are durable and easy to clean and maintain.
-
Finishes that minimize maintenance costs, improve sound attenuation/acoustics, and improve energy efficiency while integrating sustainable best practices, are a priority.
-
-
-
Work Item 5. FF&E.
-
Provide new fixtures and storage for function, and long-term durable use.
-
New built in shelving and storage.
-
New upper and lower cabinets, built-in shelving to be provided in the staff and gymnasium sink areas, library, and classrooms.
-
New cafeteria tables and new portable bleachers in the gym.
-